Project Start Date: Tue 11/16/04
Project Finish Date: Mon 1/31/05
ID | Task Name | Fixed Cost | Total Cost | Baseline Cost | Cost Variance | Actual Cost | Remaining Cost |
---|---|---|---|---|---|---|---|
1 | Start Project | $0.00 | $18,500.00 | $18,500.00 | $0.00 | $0.00 | $18,500.00 |
2 | Meet with project management team to establish roles,schedules and budgets | $0.00 | $7,500.00 | $7,500.00 | $0.00 | $0.00 | $7,500.00 |
3 | Draft milestone schedules and overall responsabilities | $0.00 | $2,500.00 | $2,500.00 | $0.00 | $0.00 | $2,500.00 |
4 | Project Kickoff meeting | $0.00 | $8,500.00 | $8,500.00 | $0.00 | $0.00 | $8,500.00 |
5 | |||||||
6 | Complete Instructional analysis | $0.00 | $38,833.55 | $38,833.55 | $0.00 | $0.00 | $38,833.55 |
7 | Team meeting-define resp and schedules | $0.00 | $8,500.00 | $8,500.00 | $0.00 | $0.00 | $8,500.00 |
8 | Complete goal analysis | $0.00 | $6,000.00 | $6,000.00 | $0.00 | $0.00 | $6,000.00 |
9 | complete task analysis | $0.00 | $6,000.00 | $6,000.00 | $0.00 | $0.00 | $6,000.00 |
10 | Present report to project management team | $0.00 | $8,500.00 | $8,500.00 | $0.00 | $0.00 | $8,500.00 |
11 | Revise as needed | $0.00 | $8,500.00 | $8,500.00 | $0.00 | $0.00 | $8,500.00 |
12 | |||||||
13 | Complete Learner & Context analysis | $0.00 | $41,500.00 | $41,500.00 | $0.00 | $0.00 | $41,500.00 |
14 | Team meeting- define resp and schedules | $0.00 | $17,000.00 | $17,000.00 | $0.00 | $0.00 | $17,000.00 |
15 | Define info needs and methods | $0.00 | $8,500.00 | $8,500.00 | $0.00 | $0.00 | $8,500.00 |
16 | Design interview questions and surveys | $0.00 | $1,000.00 | $1,000.00 | $0.00 | $0.00 | $1,000.00 |
17 | Conduct interviews abd surveys | $0.00 | $6,000.00 | $6,000.00 | $0.00 | $0.00 | $6,000.00 |
18 | Analyze and summarize results | $0.00 | $1,000.00 | $1,000.00 | $0.00 | $0.00 | $1,000.00 |
19 | Visit training sites and classrooms | $0.00 | $6,000.00 | $6,000.00 | $0.00 | $0.00 | $6,000.00 |
20 | Present analysis to management team | $0.00 | $1,000.00 | $1,000.00 | $0.00 | $0.00 | $1,000.00 |
21 | Revise Analysis | $0.00 | $1,000.00 | $1,000.00 | $0.00 | $0.00 | $1,000.00 |
22 | |||||||
23 | Develop Performance Objectives | $0.00 | $15,428.50 | $15,428.50 | $0.00 | $0.00 | $15,428.50 |
24 | Team meeting | $0.00 | $6,000.00 | $6,000.00 | $0.00 | $0.00 | $6,000.00 |
25 | Write performance objectives | $0.00 | $6,000.00 | $6,000.00 | $0.00 | $0.00 | $6,000.00 |
26 | Present to management team | $0.00 | $1,000.00 | $1,000.00 | $0.00 | $0.00 | $1,000.00 |
27 | Revise objectives | $0.00 | $1,000.00 | $1,000.00 | $0.00 | $0.00 | $1,000.00 |
28 | |||||||
29 | Develop Assessment instruments | $0.00 | $19,000.00 | $19,000.00 | $0.00 | $0.00 | $19,000.00 |
30 | Team meeting | $0.00 | $7,500.00 | $7,500.00 | $0.00 | $0.00 | $7,500.00 |
31 | Determine type of assesment | $0.00 | $3,500.00 | $3,500.00 | $0.00 | $0.00 | $3,500.00 |
32 | Develop instuments & Rubrics | $0.00 | $3,500.00 | $3,500.00 | $0.00 | $0.00 | $3,500.00 |
33 | Present assesments to management team | $0.00 | $1,000.00 | $1,000.00 | $0.00 | $0.00 | $1,000.00 |
34 | Revise assessments | $0.00 | $3,500.00 | $3,500.00 | $0.00 | $0.00 | $3,500.00 |
35 | |||||||
36 | Develop Instructional strategy | $0.00 | $23,550.00 | $23,550.00 | $0.00 | $0.00 | $23,550.00 |
37 | Team meerting | $0.00 | $8,500.00 | $8,500.00 | $0.00 | $0.00 | $8,500.00 |
38 | Select delivery system | $0.00 | $3,500.00 | $3,500.00 | $0.00 | $0.00 | $3,500.00 |
39 | sequence and cluster content | $0.00 | $3,500.00 | $3,500.00 | $0.00 | $0.00 | $3,500.00 |
40 | Identify learning components | $0.00 | $3,500.00 | $3,500.00 | $0.00 | $0.00 | $3,500.00 |
41 | Present strategy to management team | $0.00 | $1,050.00 | $1,050.00 | $0.00 | $0.00 | $1,050.00 |
42 | revise strategy | $0.00 | $3,500.00 | $3,500.00 | $0.00 | $0.00 | $3,500.00 |
43 | |||||||
44 | Develop Instructional Materials | $0.00 | $22,750.00 | $22,750.00 | $0.00 | $0.00 | $22,750.00 |
45 | Team meeting | $0.00 | $8,550.00 | $8,550.00 | $0.00 | $0.00 | $8,550.00 |
46 | Determine Content presentation needed for each objective based on strategy and learners analysis | $0.00 | $1,200.00 | $1,200.00 | $0.00 | $0.00 | $1,200.00 |
47 | Identify existing materials usable | $0.00 | $1,050.00 | $1,050.00 | $0.00 | $0.00 | $1,050.00 |
48 | Identify new materials needed | $0.00 | $1,100.00 | $1,100.00 | $0.00 | $0.00 | $1,100.00 |
49 | Produce Draft of new materials | $0.00 | $1,000.00 | $1,000.00 | $0.00 | $0.00 | $1,000.00 |
50 | Review revise new materials | $0.00 | $3,700.00 | $3,700.00 | $0.00 | $0.00 | $3,700.00 |
51 | Produce final draft new materials | $0.00 | $1,200.00 | $1,200.00 | $0.00 | $0.00 | $1,200.00 |
52 | Present materials to management team | $0.00 | $1,050.00 | $1,050.00 | $0.00 | $0.00 | $1,050.00 |
53 | Revise materials as needed | $0.00 | $3,900.00 | $3,900.00 | $0.00 | $0.00 | $3,900.00 |
54 | |||||||
55 | Conduct Pre-use Evaluations | $0.00 | $29,400.00 | $29,400.00 | $0.00 | $0.00 | $29,400.00 |
56 | Legal review | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |
57 | one on one with 3 learners | $0.00 | $6,000.00 | $6,000.00 | $0.00 | $0.00 | $6,000.00 |
58 | revise instruction | $0.00 | $6,200.00 | $6,200.00 | $0.00 | $0.00 | $6,200.00 |
59 | Small group evaluations | $0.00 | $1,000.00 | $1,000.00 | $0.00 | $0.00 | $1,000.00 |
60 | Revise instruction | $0.00 | $6,200.00 | $6,200.00 | $0.00 | $0.00 | $6,200.00 |
61 | Summarize findings | $0.00 | $5,000.00 | $5,000.00 | $0.00 | $0.00 | $5,000.00 |
62 | Present findings to project management | $0.00 | $5,000.00 | $5,000.00 | $0.00 | $0.00 | $5,000.00 |
63 | |||||||
64 | |||||||
65 | Impliment training | $0.00 | $10,000.00 | $10,000.00 | $0.00 | $0.00 | $10,000.00 |
66 | Train teachers | $0.00 | $5,000.00 | $5,000.00 | $0.00 | $0.00 | $5,000.00 |
67 | Train nurses | $0.00 | $5,000.00 | $5,000.00 | $0.00 | $0.00 | $5,000.00 |
68 | |||||||
69 | Training Follow up | $0.00 | $15,000.00 | $15,000.00 | $0.00 | $0.00 | $15,000.00 |
70 | Design and impliment learner survey | $0.00 | $5,000.00 | $5,000.00 | $0.00 | $0.00 | $5,000.00 |
71 | Establish complaint reporting system to project management team | $0.00 | $5,000.00 | $5,000.00 | $0.00 | $0.00 | $5,000.00 |
72 | Final Budget-Expense report | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 | $0.00 |