Project Start Date: Tue 11/16/04
Project Finish Date: Mon 1/31/05
Resources and Assignments | Start | Finish | Work |
---|---|---|---|
Project Manager | Tue 11/16/04 | Mon 1/31/05 | 279.05 hrs |
Meet with project management team to establish roles,schedules and budgets | Tue 11/16/04 | Tue 11/16/04 | 4 hrs |
Project Kickoff meeting | Fri 11/19/04 | Fri 11/19/04 | 3 hrs |
Team meeting-define resp and schedules | Fri 11/19/04 | Fri 11/19/04 | 4 hrs |
Complete Instructional analysis | Fri 11/19/04 | Thu 11/25/04 | 5.33 hrs |
Complete goal analysis | Mon 11/22/04 | Mon 11/22/04 | 8 hrs |
complete task analysis | Tue 11/23/04 | Tue 11/23/04 | 8 hrs |
Revise as needed | Wed 11/24/04 | Wed 11/24/04 | 1 hr |
Team meeting- define resp and schedules | Thu 11/25/04 | Thu 11/25/04 | 4 hrs |
Define info needs and methods | Thu 11/25/04 | Fri 11/26/04 | 4 hrs |
Conduct interviews abd surveys | Fri 11/26/04 | Wed 12/1/04 | 20 hrs |
Visit training sites and classrooms | Fri 11/26/04 | Fri 12/3/04 | 40 hrs |
Write performance objectives | Tue 12/7/04 | Wed 12/8/04 | 8 hrs |
Develop Performance Objectives | Mon 12/6/04 | Thu 12/9/04 | 5.71 hrs |
one on one with 3 learners | Thu 1/6/05 | Fri 1/7/05 | 8 hrs |
Summarize findings | Wed 1/12/05 | Thu 1/13/05 | 8 hrs |
revise instruction | Fri 1/7/05 | Mon 1/10/05 | 8 hrs |
Revise instruction | Tue 1/11/05 | Wed 1/12/05 | 8 hrs |
Train nurses | Thu 1/20/05 | Thu 1/27/05 | 40 hrs |
Train teachers | Thu 1/13/05 | Thu 1/20/05 | 40 hrs |
Training Follow up | Thu 1/27/05 | Mon 1/31/05 | 16 hrs |
Design and impliment learner survey | Thu 1/27/05 | Fri 1/28/05 | 8 hrs |
Establish complaint reporting system to project management team | Fri 1/28/05 | Mon 1/31/05 | 4 hrs |
Present findings to project management | Thu 1/13/05 | Thu 1/13/05 | 4 hrs |
Team meeting | Mon 12/6/04 | Tue 12/7/04 | 4 hrs |
Team meeting | Thu 12/9/04 | Thu 12/9/04 | 4 hrs |
Team meerting | Tue 12/14/04 | Wed 12/15/04 | 4 hrs |
Team meeting | Mon 12/20/04 | Tue 12/21/04 | 4 hrs |
Present report to project management team | Wed 11/24/04 | Wed 11/24/04 | 4 hrs |
NHCS Assist Supt | Tue 11/16/04 | Wed 11/24/04 | 32 hrs |
Meet with project management team to establish roles,schedules and budgets | Tue 11/16/04 | Tue 11/16/04 | 8 hrs |
Draft milestone schedules and overall responsabilities | Wed 11/17/04 | Thu 11/18/04 | 16 hrs |
Project Kickoff meeting | Fri 11/19/04 | Fri 11/19/04 | 4 hrs |
Present report to project management team | Wed 11/24/04 | Wed 11/24/04 | 4 hrs |
Maxim Director Nursing | Tue 11/16/04 | Mon 1/31/05 | 36 hrs |
Meet with project management team to establish roles,schedules and budgets | Tue 11/16/04 | Tue 11/16/04 | 8 hrs |
Draft milestone schedules and overall responsabilities | Wed 11/17/04 | Thu 11/18/04 | 16 hrs |
Project Kickoff meeting | Fri 11/19/04 | Fri 11/19/04 | 4 hrs |
Establish complaint reporting system to project management team | Fri 1/28/05 | Mon 1/31/05 | 4 hrs |
Present report to project management team | Wed 11/24/04 | Wed 11/24/04 | 4 hrs |
UNCW Dept Chair | Tue 11/16/04 | Tue 1/4/05 | 104.13 hrs |
Meet with project management team to establish roles,schedules and budgets | Tue 11/16/04 | Tue 11/16/04 | 4 hrs |
Draft milestone schedules and overall responsabilities | Wed 11/17/04 | Wed 11/17/04 | 2 hrs |
Project Kickoff meeting | Fri 11/19/04 | Fri 11/19/04 | 4 hrs |
Team meeting-define resp and schedules | Fri 11/19/04 | Fri 11/19/04 | 4 hrs |
Complete Instructional analysis | Fri 11/19/04 | Thu 11/25/04 | 2.13 hrs |
Revise as needed | Wed 11/24/04 | Wed 11/24/04 | 4 hrs |
Team meeting- define resp and schedules | Thu 11/25/04 | Thu 11/25/04 | 4 hrs |
Define info needs and methods | Thu 11/25/04 | Fri 11/26/04 | 4 hrs |
Determine type of assesment | Thu 12/9/04 | Fri 12/10/04 | 4 hrs |
Develop instuments & Rubrics | Fri 12/10/04 | Mon 12/13/04 | 8 hrs |
Revise assessments | Mon 12/13/04 | Tue 12/14/04 | 4 hrs |
Select delivery system | Thu 12/16/04 | Fri 12/17/04 | 8 hrs |
sequence and cluster content | Wed 12/15/04 | Thu 12/16/04 | 8 hrs |
revise strategy | Fri 12/17/04 | Mon 12/20/04 | 8 hrs |
Identify learning components | Thu 12/16/04 | Fri 12/17/04 | 8 hrs |
Review revise new materials | Thu 12/30/04 | Thu 12/30/04 | 4 hrs |
Revise materials as needed | Mon 1/3/05 | Tue 1/4/05 | 8 hrs |
Team meeting | Thu 12/9/04 | Thu 12/9/04 | 4 hrs |
Team meerting | Tue 12/14/04 | Wed 12/15/04 | 4 hrs |
Team meeting | Mon 12/20/04 | Tue 12/21/04 | 4 hrs |
Present report to project management team | Wed 11/24/04 | Wed 11/24/04 | 4 hrs |
UNCW Intern | Fri 11/19/04 | Wed 1/12/05 | 214.67 hrs |
Project Kickoff meeting | Fri 11/19/04 | Fri 11/19/04 | 4 hrs |
Team meeting-define resp and schedules | Fri 11/19/04 | Fri 11/19/04 | 4 hrs |
Complete Instructional analysis | Fri 11/19/04 | Thu 11/25/04 | 10.67 hrs |
Complete goal analysis | Mon 11/22/04 | Mon 11/22/04 | 4 hrs |
complete task analysis | Tue 11/23/04 | Tue 11/23/04 | 8 hrs |
Present report to project management team | Wed 11/24/04 | Wed 11/24/04 | 4 hrs |
Revise as needed | Wed 11/24/04 | Thu 11/25/04 | 8 hrs |
Team meeting- define resp and schedules | Thu 11/25/04 | Thu 11/25/04 | 4 hrs |
Define info needs and methods | Thu 11/25/04 | Fri 11/26/04 | 4 hrs |
Design interview questions and surveys | Fri 11/26/04 | Fri 11/26/04 | 4 hrs |
Conduct interviews abd surveys | Fri 11/26/04 | Mon 11/29/04 | 8 hrs |
Analyze and summarize results | Wed 12/1/04 | Wed 12/1/04 | 4 hrs |
Visit training sites and classrooms | Fri 11/26/04 | Mon 11/29/04 | 8 hrs |
Present analysis to management team | Fri 12/3/04 | Mon 12/6/04 | 4 hrs |
Revise Analysis | Mon 12/6/04 | Mon 12/6/04 | 4 hrs |
Write performance objectives | Tue 12/7/04 | Tue 12/7/04 | 4 hrs |
Present to management team | Wed 12/8/04 | Wed 12/8/04 | 4 hrs |
Revise objectives | Wed 12/8/04 | Thu 12/9/04 | 4 hrs |
Determine type of assesment | Thu 12/9/04 | Fri 12/10/04 | 4 hrs |
Develop instuments & Rubrics | Fri 12/10/04 | Mon 12/13/04 | 8 hrs |
Present assesments to management team | Mon 12/13/04 | Mon 12/13/04 | 4 hrs |
Revise assessments | Mon 12/13/04 | Tue 12/14/04 | 4 hrs |
Select delivery system | Thu 12/16/04 | Thu 12/16/04 | 4 hrs |
sequence and cluster content | Wed 12/15/04 | Thu 12/16/04 | 8 hrs |
Present strategy to management team | Fri 12/17/04 | Fri 12/17/04 | 4 hrs |
revise strategy | Fri 12/17/04 | Mon 12/20/04 | 4 hrs |
Determine Content presentation needed for each objective based on strategy and learners analysis | Tue 12/21/04 | Tue 12/21/04 | 4 hrs |
Identify learning components | Thu 12/16/04 | Fri 12/17/04 | 8 hrs |
Identify new materials needed | Wed 12/22/04 | Thu 12/23/04 | 4 hrs |
Identify existing materials usable | Wed 12/22/04 | Wed 12/22/04 | 4 hrs |
Review revise new materials | Thu 12/30/04 | Thu 12/30/04 | 4 hrs |
Produce final draft new materials | Fri 12/31/04 | Mon 1/3/05 | 8 hrs |
Present materials to management team | Mon 1/3/05 | Mon 1/3/05 | 4 hrs |
Revise materials as needed | Mon 1/3/05 | Tue 1/4/05 | 8 hrs |
one on one with 3 learners | Thu 1/6/05 | Fri 1/7/05 | 4 hrs |
Small group evaluations | Mon 1/10/05 | Tue 1/11/05 | 4 hrs |
revise instruction | Fri 1/7/05 | Mon 1/10/05 | 8 hrs |
Revise instruction | Tue 1/11/05 | Wed 1/12/05 | 8 hrs |
Team meeting | Mon 12/6/04 | Tue 12/7/04 | 4 hrs |
Team meerting | Tue 12/14/04 | Wed 12/15/04 | 4 hrs |
Team meeting | Mon 12/20/04 | Tue 12/21/04 | 4 hrs |
UNCW Content Development Specialists | Fri 12/17/04 | Wed 1/12/05 | 108 hrs |
Present strategy to management team | Fri 12/17/04 | Fri 12/17/04 | 2 hrs |
Determine Content presentation needed for each objective based on strategy and learners analysis | Tue 12/21/04 | Wed 12/22/04 | 8 hrs |
Identify new materials needed | Wed 12/22/04 | Thu 12/23/04 | 4 hrs |
Identify existing materials usable | Wed 12/22/04 | Wed 12/22/04 | 2 hrs |
Produce Draft of new materials | Thu 12/23/04 | Thu 12/30/04 | 40 hrs |
Review revise new materials | Thu 12/30/04 | Fri 12/31/04 | 8 hrs |
Produce final draft new materials | Fri 12/31/04 | Mon 1/3/05 | 8 hrs |
Present materials to management team | Mon 1/3/05 | Mon 1/3/05 | 2 hrs |
Revise materials as needed | Mon 1/3/05 | Wed 1/5/05 | 16 hrs |
revise instruction | Fri 1/7/05 | Mon 1/10/05 | 8 hrs |
Revise instruction | Tue 1/11/05 | Wed 1/12/05 | 8 hrs |
Team meeting | Mon 12/20/04 | Mon 12/20/04 | 2 hrs |
Maxim Nurse | Fri 11/19/04 | Wed 1/5/05 | 84 hrs |
Project Kickoff meeting | Fri 11/19/04 | Fri 11/19/04 | 4 hrs |
Team meeting- define resp and schedules | Thu 11/25/04 | Thu 11/25/04 | 4 hrs |
Define info needs and methods | Thu 11/25/04 | Fri 11/26/04 | 4 hrs |
Determine type of assesment | Thu 12/9/04 | Thu 12/9/04 | 2 hrs |
Develop instuments & Rubrics | Fri 12/10/04 | Fri 12/10/04 | 4 hrs |
Present assesments to management team | Mon 12/13/04 | Mon 12/13/04 | 2 hrs |
Revise assessments | Mon 12/13/04 | Mon 12/13/04 | 2 hrs |
Select delivery system | Thu 12/16/04 | Thu 12/16/04 | 2 hrs |
sequence and cluster content | Wed 12/15/04 | Wed 12/15/04 | 4 hrs |
Present strategy to management team | Fri 12/17/04 | Fri 12/17/04 | 2 hrs |
revise strategy | Fri 12/17/04 | Mon 12/20/04 | 4 hrs |
Identify learning components | Thu 12/16/04 | Fri 12/17/04 | 8 hrs |
Identify new materials needed | Wed 12/22/04 | Thu 12/23/04 | 4 hrs |
Identify existing materials usable | Wed 12/22/04 | Wed 12/22/04 | 2 hrs |
Review revise new materials | Thu 12/30/04 | Thu 12/30/04 | 4 hrs |
Present materials to management team | Mon 1/3/05 | Mon 1/3/05 | 4 hrs |
Revise materials as needed | Mon 1/3/05 | Wed 1/5/05 | 16 hrs |
Team meeting | Thu 12/9/04 | Thu 12/9/04 | 4 hrs |
Team meerting | Tue 12/14/04 | Wed 12/15/04 | 4 hrs |
Team meeting | Mon 12/20/04 | Tue 12/21/04 | 4 hrs |
NHCS Teacher | Fri 11/19/04 | Wed 1/5/05 | 84 hrs |
Project Kickoff meeting | Fri 11/19/04 | Fri 11/19/04 | 4 hrs |
Determine type of assesment | Thu 12/9/04 | Fri 12/10/04 | 4 hrs |
Develop instuments & Rubrics | Fri 12/10/04 | Mon 12/13/04 | 8 hrs |
Present assesments to management team | Mon 12/13/04 | Mon 12/13/04 | 2 hrs |
Revise assessments | Mon 12/13/04 | Tue 12/14/04 | 8 hrs |
Select delivery system | Thu 12/16/04 | Thu 12/16/04 | 4 hrs |
sequence and cluster content | Wed 12/15/04 | Wed 12/15/04 | 4 hrs |
Present strategy to management team | Fri 12/17/04 | Fri 12/17/04 | 2 hrs |
revise strategy | Fri 12/17/04 | Mon 12/20/04 | 4 hrs |
Identify learning components | Thu 12/16/04 | Fri 12/17/04 | 8 hrs |
Identify existing materials usable | Wed 12/22/04 | Wed 12/22/04 | 4 hrs |
Identify new materials needed | Wed 12/22/04 | Thu 12/23/04 | 4 hrs |
Review revise new materials | Thu 12/30/04 | Thu 12/30/04 | 4 hrs |
Present materials to management team | Mon 1/3/05 | Mon 1/3/05 | 2 hrs |
Revise materials as needed | Mon 1/3/05 | Wed 1/5/05 | 16 hrs |
Team meeting | Thu 12/9/04 | Thu 12/9/04 | 2 hrs |
Team meerting | Tue 12/14/04 | Tue 12/14/04 | 2 hrs |
Team meeting | Mon 12/20/04 | Mon 12/20/04 | 2 hrs |
Maim Accountant | Fri 11/19/04 | Mon 1/31/05 | 12 hrs |
Project Kickoff meeting | Fri 11/19/04 | Fri 11/19/04 | 4 hrs |
Team meeting- define resp and schedules | Thu 11/25/04 | Thu 11/25/04 | 4 hrs |
Final Budget-Expense report | Mon 1/31/05 | Mon 1/31/05 | 4 hrs |
Maxim Lawyer | Wed 1/5/05 | Thu 1/6/05 | 8 hrs |
Legal review | Wed 1/5/05 | Thu 1/6/05 | 8 hrs |