Project


Project Start Date: Tue 11/16/04
Project Finish Date: Mon 1/31/05

Who Does What

Resources and AssignmentsStartFinishWork
Project Manager
Tue 11/16/04Mon 1/31/05279.05 hrs
Meet with project management team to establish roles,schedules and budgets
Tue 11/16/04Tue 11/16/044 hrs
Project Kickoff meeting
Fri 11/19/04Fri 11/19/043 hrs
Team meeting-define resp and schedules
Fri 11/19/04Fri 11/19/044 hrs
Complete Instructional analysis
Fri 11/19/04Thu 11/25/045.33 hrs
Complete goal analysis
Mon 11/22/04Mon 11/22/048 hrs
complete task analysis
Tue 11/23/04Tue 11/23/048 hrs
Revise as needed
Wed 11/24/04Wed 11/24/041 hr
Team meeting- define resp and schedules
Thu 11/25/04Thu 11/25/044 hrs
Define info needs and methods
Thu 11/25/04Fri 11/26/044 hrs
Conduct interviews abd surveys
Fri 11/26/04Wed 12/1/0420 hrs
Visit training sites and classrooms
Fri 11/26/04Fri 12/3/0440 hrs
Write performance objectives
Tue 12/7/04Wed 12/8/048 hrs
Develop Performance Objectives
Mon 12/6/04Thu 12/9/045.71 hrs
one on one with 3 learners
Thu 1/6/05Fri 1/7/058 hrs
Summarize findings
Wed 1/12/05Thu 1/13/058 hrs
revise instruction
Fri 1/7/05Mon 1/10/058 hrs
Revise instruction
Tue 1/11/05Wed 1/12/058 hrs
Train nurses
Thu 1/20/05Thu 1/27/0540 hrs
Train teachers
Thu 1/13/05Thu 1/20/0540 hrs
Training Follow up
Thu 1/27/05Mon 1/31/0516 hrs
Design and impliment learner survey
Thu 1/27/05Fri 1/28/058 hrs
Establish complaint reporting system to project management team
Fri 1/28/05Mon 1/31/054 hrs
Present findings to project management
Thu 1/13/05Thu 1/13/054 hrs
Team meeting
Mon 12/6/04Tue 12/7/044 hrs
Team meeting
Thu 12/9/04Thu 12/9/044 hrs
Team meerting
Tue 12/14/04Wed 12/15/044 hrs
Team meeting
Mon 12/20/04Tue 12/21/044 hrs
Present report to project management team
Wed 11/24/04Wed 11/24/044 hrs
NHCS Assist Supt
Tue 11/16/04Wed 11/24/0432 hrs
Meet with project management team to establish roles,schedules and budgets
Tue 11/16/04Tue 11/16/048 hrs
Draft milestone schedules and overall responsabilities
Wed 11/17/04Thu 11/18/0416 hrs
Project Kickoff meeting
Fri 11/19/04Fri 11/19/044 hrs
Present report to project management team
Wed 11/24/04Wed 11/24/044 hrs
Maxim Director Nursing
Tue 11/16/04Mon 1/31/0536 hrs
Meet with project management team to establish roles,schedules and budgets
Tue 11/16/04Tue 11/16/048 hrs
Draft milestone schedules and overall responsabilities
Wed 11/17/04Thu 11/18/0416 hrs
Project Kickoff meeting
Fri 11/19/04Fri 11/19/044 hrs
Establish complaint reporting system to project management team
Fri 1/28/05Mon 1/31/054 hrs
Present report to project management team
Wed 11/24/04Wed 11/24/044 hrs
UNCW Dept Chair
Tue 11/16/04Tue 1/4/05104.13 hrs
Meet with project management team to establish roles,schedules and budgets
Tue 11/16/04Tue 11/16/044 hrs
Draft milestone schedules and overall responsabilities
Wed 11/17/04Wed 11/17/042 hrs
Project Kickoff meeting
Fri 11/19/04Fri 11/19/044 hrs
Team meeting-define resp and schedules
Fri 11/19/04Fri 11/19/044 hrs
Complete Instructional analysis
Fri 11/19/04Thu 11/25/042.13 hrs
Revise as needed
Wed 11/24/04Wed 11/24/044 hrs
Team meeting- define resp and schedules
Thu 11/25/04Thu 11/25/044 hrs
Define info needs and methods
Thu 11/25/04Fri 11/26/044 hrs
Determine type of assesment
Thu 12/9/04Fri 12/10/044 hrs
Develop instuments & Rubrics
Fri 12/10/04Mon 12/13/048 hrs
Revise assessments
Mon 12/13/04Tue 12/14/044 hrs
Select delivery system
Thu 12/16/04Fri 12/17/048 hrs
sequence and cluster content
Wed 12/15/04Thu 12/16/048 hrs
revise strategy
Fri 12/17/04Mon 12/20/048 hrs
Identify learning components
Thu 12/16/04Fri 12/17/048 hrs
Review revise new materials
Thu 12/30/04Thu 12/30/044 hrs
Revise materials as needed
Mon 1/3/05Tue 1/4/058 hrs
Team meeting
Thu 12/9/04Thu 12/9/044 hrs
Team meerting
Tue 12/14/04Wed 12/15/044 hrs
Team meeting
Mon 12/20/04Tue 12/21/044 hrs
Present report to project management team
Wed 11/24/04Wed 11/24/044 hrs
UNCW Intern
Fri 11/19/04Wed 1/12/05214.67 hrs
Project Kickoff meeting
Fri 11/19/04Fri 11/19/044 hrs
Team meeting-define resp and schedules
Fri 11/19/04Fri 11/19/044 hrs
Complete Instructional analysis
Fri 11/19/04Thu 11/25/0410.67 hrs
Complete goal analysis
Mon 11/22/04Mon 11/22/044 hrs
complete task analysis
Tue 11/23/04Tue 11/23/048 hrs
Present report to project management team
Wed 11/24/04Wed 11/24/044 hrs
Revise as needed
Wed 11/24/04Thu 11/25/048 hrs
Team meeting- define resp and schedules
Thu 11/25/04Thu 11/25/044 hrs
Define info needs and methods
Thu 11/25/04Fri 11/26/044 hrs
Design interview questions and surveys
Fri 11/26/04Fri 11/26/044 hrs
Conduct interviews abd surveys
Fri 11/26/04Mon 11/29/048 hrs
Analyze and summarize results
Wed 12/1/04Wed 12/1/044 hrs
Visit training sites and classrooms
Fri 11/26/04Mon 11/29/048 hrs
Present analysis to management team
Fri 12/3/04Mon 12/6/044 hrs
Revise Analysis
Mon 12/6/04Mon 12/6/044 hrs
Write performance objectives
Tue 12/7/04Tue 12/7/044 hrs
Present to management team
Wed 12/8/04Wed 12/8/044 hrs
Revise objectives
Wed 12/8/04Thu 12/9/044 hrs
Determine type of assesment
Thu 12/9/04Fri 12/10/044 hrs
Develop instuments & Rubrics
Fri 12/10/04Mon 12/13/048 hrs
Present assesments to management team
Mon 12/13/04Mon 12/13/044 hrs
Revise assessments
Mon 12/13/04Tue 12/14/044 hrs
Select delivery system
Thu 12/16/04Thu 12/16/044 hrs
sequence and cluster content
Wed 12/15/04Thu 12/16/048 hrs
Present strategy to management team
Fri 12/17/04Fri 12/17/044 hrs
revise strategy
Fri 12/17/04Mon 12/20/044 hrs
Determine Content presentation needed for each objective based on strategy and learners analysis
Tue 12/21/04Tue 12/21/044 hrs
Identify learning components
Thu 12/16/04Fri 12/17/048 hrs
Identify new materials needed
Wed 12/22/04Thu 12/23/044 hrs
Identify existing materials usable
Wed 12/22/04Wed 12/22/044 hrs
Review revise new materials
Thu 12/30/04Thu 12/30/044 hrs
Produce final draft new materials
Fri 12/31/04Mon 1/3/058 hrs
Present materials to management team
Mon 1/3/05Mon 1/3/054 hrs
Revise materials as needed
Mon 1/3/05Tue 1/4/058 hrs
one on one with 3 learners
Thu 1/6/05Fri 1/7/054 hrs
Small group evaluations
Mon 1/10/05Tue 1/11/054 hrs
revise instruction
Fri 1/7/05Mon 1/10/058 hrs
Revise instruction
Tue 1/11/05Wed 1/12/058 hrs
Team meeting
Mon 12/6/04Tue 12/7/044 hrs
Team meerting
Tue 12/14/04Wed 12/15/044 hrs
Team meeting
Mon 12/20/04Tue 12/21/044 hrs
UNCW Content Development Specialists
Fri 12/17/04Wed 1/12/05108 hrs
Present strategy to management team
Fri 12/17/04Fri 12/17/042 hrs
Determine Content presentation needed for each objective based on strategy and learners analysis
Tue 12/21/04Wed 12/22/048 hrs
Identify new materials needed
Wed 12/22/04Thu 12/23/044 hrs
Identify existing materials usable
Wed 12/22/04Wed 12/22/042 hrs
Produce Draft of new materials
Thu 12/23/04Thu 12/30/0440 hrs
Review revise new materials
Thu 12/30/04Fri 12/31/048 hrs
Produce final draft new materials
Fri 12/31/04Mon 1/3/058 hrs
Present materials to management team
Mon 1/3/05Mon 1/3/052 hrs
Revise materials as needed
Mon 1/3/05Wed 1/5/0516 hrs
revise instruction
Fri 1/7/05Mon 1/10/058 hrs
Revise instruction
Tue 1/11/05Wed 1/12/058 hrs
Team meeting
Mon 12/20/04Mon 12/20/042 hrs
Maxim Nurse
Fri 11/19/04Wed 1/5/0584 hrs
Project Kickoff meeting
Fri 11/19/04Fri 11/19/044 hrs
Team meeting- define resp and schedules
Thu 11/25/04Thu 11/25/044 hrs
Define info needs and methods
Thu 11/25/04Fri 11/26/044 hrs
Determine type of assesment
Thu 12/9/04Thu 12/9/042 hrs
Develop instuments & Rubrics
Fri 12/10/04Fri 12/10/044 hrs
Present assesments to management team
Mon 12/13/04Mon 12/13/042 hrs
Revise assessments
Mon 12/13/04Mon 12/13/042 hrs
Select delivery system
Thu 12/16/04Thu 12/16/042 hrs
sequence and cluster content
Wed 12/15/04Wed 12/15/044 hrs
Present strategy to management team
Fri 12/17/04Fri 12/17/042 hrs
revise strategy
Fri 12/17/04Mon 12/20/044 hrs
Identify learning components
Thu 12/16/04Fri 12/17/048 hrs
Identify new materials needed
Wed 12/22/04Thu 12/23/044 hrs
Identify existing materials usable
Wed 12/22/04Wed 12/22/042 hrs
Review revise new materials
Thu 12/30/04Thu 12/30/044 hrs
Present materials to management team
Mon 1/3/05Mon 1/3/054 hrs
Revise materials as needed
Mon 1/3/05Wed 1/5/0516 hrs
Team meeting
Thu 12/9/04Thu 12/9/044 hrs
Team meerting
Tue 12/14/04Wed 12/15/044 hrs
Team meeting
Mon 12/20/04Tue 12/21/044 hrs
NHCS Teacher
Fri 11/19/04Wed 1/5/0584 hrs
Project Kickoff meeting
Fri 11/19/04Fri 11/19/044 hrs
Determine type of assesment
Thu 12/9/04Fri 12/10/044 hrs
Develop instuments & Rubrics
Fri 12/10/04Mon 12/13/048 hrs
Present assesments to management team
Mon 12/13/04Mon 12/13/042 hrs
Revise assessments
Mon 12/13/04Tue 12/14/048 hrs
Select delivery system
Thu 12/16/04Thu 12/16/044 hrs
sequence and cluster content
Wed 12/15/04Wed 12/15/044 hrs
Present strategy to management team
Fri 12/17/04Fri 12/17/042 hrs
revise strategy
Fri 12/17/04Mon 12/20/044 hrs
Identify learning components
Thu 12/16/04Fri 12/17/048 hrs
Identify existing materials usable
Wed 12/22/04Wed 12/22/044 hrs
Identify new materials needed
Wed 12/22/04Thu 12/23/044 hrs
Review revise new materials
Thu 12/30/04Thu 12/30/044 hrs
Present materials to management team
Mon 1/3/05Mon 1/3/052 hrs
Revise materials as needed
Mon 1/3/05Wed 1/5/0516 hrs
Team meeting
Thu 12/9/04Thu 12/9/042 hrs
Team meerting
Tue 12/14/04Tue 12/14/042 hrs
Team meeting
Mon 12/20/04Mon 12/20/042 hrs
Maim Accountant
Fri 11/19/04Mon 1/31/0512 hrs
Project Kickoff meeting
Fri 11/19/04Fri 11/19/044 hrs
Team meeting- define resp and schedules
Thu 11/25/04Thu 11/25/044 hrs
Final Budget-Expense report
Mon 1/31/05Mon 1/31/054 hrs
Maxim Lawyer
Wed 1/5/05Thu 1/6/058 hrs
Legal review
Wed 1/5/05Thu 1/6/058 hrs